Pipeline Anti‑corrosion Heat‑shrinkable Tape Series
Pipeline Protection Material Product Series
Visco‑elastic Product Series
PET Product Series
Adhesive Product Series
Engineering Technical Service Series
Heavy‑duty Anti‑corrosion Series
Protection Product Series
Polyurethane Product Series
CasesOil&Gas PipelineDC Interference Mitigation Project for Meishi Branch Pipeline & AC Interference Mitigation Projects for Huizhou, Guangzhou and Foshan

DC Interference Mitigation Project for Meishi Branch Pipeline & AC Interference Mitigation Projects for Huizhou, Guangzhou and Foshan

Construction Scheme: Zinc Band Drainage + New Cathodic Protection Station Construction + Project Acceptance Report
Construction Conclusion:One new cathodic protection station was built, and 8 sets of zinc band drainage groundbeds with a total length of 1900 meters were installed.

新增阴保站施工周边环境信息图
排流地床开挖
电缆接线防腐
排流量测试
长效参比和试片安装
钻井施工
防腐层检查
恒电位仪A机恒流8A运行
测试桩断电电位曲线图
新增阴保站施工周边环境信息图
排流地床开挖
电缆接线防腐
排流量测试
长效参比和试片安装
钻井施工
防腐层检查
恒电位仪A机恒流8A运行
测试桩断电电位曲线图

Project Introduction

Based on data from cathodic protection remote monitoring equipment, special stray current surveys and quarterly cathodic protection inspections, Guangdong Dapeng LNG Co., Ltd. found three under-protected sections with substandard cathodic protection potential on the Meishi Branch Pipeline. Four segments of the Huizhou Branch Pipeline had induced AC voltage exceeding 15 V, with a maximum value of 17.35 V. Three pipeline sections in Guangzhou and Shenzhen showed excessive AC current density. A 1 cm² corrosion coupon was buried for long-term monitoring (more than 15 days), followed by 24-hour continuous measurement. The average interference current density was 527 A/m², and the peak value reached 636 A/m². After on-site verification, construction works for DC interference mitigation on the Meishi Branch Pipeline and AC drainage remediation in Huizhou, Guangzhou and Shenzhen are required to reduce pipeline corrosion risks.

  • Project Name
    DC Interference Mitigation Project for Meishi Branch Pipeline & AC Interference Mitigation Projects for Huizhou, Guangzhou and Foshan
  • Installation Time
    July 03, 2024
  • Project Notes
    Shenzhen City, Guangdong Province

Consult Now for Customized Solutions

Our professional team provides 24/7 support for you.
I confirm that I have read, understood and agree to Terms of Service,and agree to Privacy Policy.